Work camp at the Site C dam project near Fort St. John. (BC HYDRO)

B.C. asks utilities commission to review Site C

The regulator will assess the project’s economic viability, with a final report in three months.

The New Democrat government has asked the province’s utilities commission to review the $8.8-billion Site C dam, throwing into doubt one of former premier Christy Clark’s major accomplishments.

Energy Minister Michelle Mungall says the regulator will be tasked with determining the economic viability of the megaproject, with interim results in six weeks and a final report in three months.

Mungall says the commission has been asked to confirm whether BC Hydro is on target to complete Site C on budget and by 2024, and provide advice on whether to proceed, suspend or terminate it.

The NDP campaigned on sending the project to the commission, a practice that was once standard in B.C., before the previous Liberal government’s clean energy laws allowed some major projects to bypass the regulatory agency.

The dam is two years into construction and employs more than 2,200 people in northeastern B.C., and former BC Hydro CEO Jessica McDonald has warned that a one-year delay would cost $630 million.

It would be the third dam on the Peace River, flooding an 83-kilometre stretch of valley, and has faced fierce opposition from local First Nations, landowners and farmers.

The Canadian Press

Just Posted

More Parksville Qualicum school families to get hampers this Christmas

School district, business giving project exceeds last year’s total

#MeToo at work: How reporting sexual harassment works – and how it doesn’t

British Columbians have four options to report harassment or assault, but none of them are easy

RCMP investigate mailbox theft in Qualicum Beach area

Four rural community boxes pried open overnight Dec. 12

#MeToo at work: B.C. women share horrifyingly common sexual assaults

It happens to more people than you might think and impacts women inside and outside of the workplace

RDN to proceed with Bowser Wastewater Project

Board endorse plan to work on design, tendering and construction of the sewer system

Qualicum Beach dancers shine in showcase

QB School of Dance hosts annual winter show

Multiple-vehicle crash in Nanaimo shuts down section of highway

Emergency crews responded at about 2:50 p.m. Friday, Dec. 15, to a four-vehicle collision

Guests invited to free Christmas dinner in Qualicum Beach

Christian Fellowship Centre hosts 20th annual feast

Court denies WestJet’s bid to toss out discrimination lawsuit of former worker

Mandalena Lewis is suing WestJet over allegations of gender-based discrimination

Police continue to seek missing Qualicum Beach woman

Oceanside RCMP requesting public assistance in locating Carmel Georgina Gilmour

MAP: Christmas lights displays to check out in Parksville Qualicum Beach

The NEWS is compiling a list/map to aid in the search for great local Christmas displays

Two-car crash in front of Parksville fire department

One woman checked for minor injuries

Sagmoen neighbours recall alleged hammer attack

Woman was screaming outside Maple Ridge townhouse in 2013

VIDEO: 3 months later, rescued sea lion released back into ocean

The young animal was found in Campbell River three months ago

Most Read