Vancouver Island school upgrade $1.4 million over budget and no one noticed

The original construction budget was not adjusted to account for some expenses

Following the completion of the Georges P. Vanier seismic upgrades in October, the school district determined they had gone approximately $1,450,000 over budget.

The $33.1 million upgrade project started in 2016 and was completed in phases, including adding additional classrooms, specialized spaces such as a new auditorium and an Aboriginal education room, and relocating the library. The project also included upgrading the school’s mechanical and electrical systems that were nearly 50-years-old. Approximately $32.8 million for the project was provided by the Ministry of Education and around $1 million was from the school district.

According to SD71 secretary-treasurer Nicole Bittante, the school district did not realize they were over budget until the project was completed as they thought all expenditures had been accounted for.

“While this overspend was not identified until the project was completed, it was thought all along that the budget allowed for these expenditures,” said Bittante. “District staff were reconciling all of their amounts to the original budget. In the meantime, the original budget hadn’t been adjusted for various items. So it appeared during the term of the project that the project was on schedule and on budget.”

Bittante outlined the areas where the overspending happened, with the most significant portion being the GST.

“The original construction budget back in 2015 that was provided to the construction company did not include GST, however, the budget should have included the non-rebatable portion of GST,” she said. “There’s a portion that the district pays and then receives back in a rebate.”

The non-rebatable portion of GST was a cost to the district of approximately $477,000.

Other areas where there was overspending included a portion of the director of operations’ salary and some wages for a custodian which were not reduced from the construction budget, totaling $196,000.

In 2017, the gymnasium walls required repairs due to a safety concern, and while the Ministry provided $220,000 to address the issue, the fix still went $117,000 over budget.

The costs for the initial project planning, totaling approximately $152,000, were also not removed from the construction budget. Another $40,000 was listed as “other balancing factors,” and the project went an additional $465,000 over budget as this amount was not covered by the risk reserve.

“The $33 million included a $4 million risk reserve. It wasn’t guaranteed funding, it was an amount that was awarded through the ministry, but it was an amount that we had to apply for and there were criteria attached to it,” said Bittante. “I think the issue is that we, in our budget, gave the $4 million to the construction company and it was spent.”

The school district was only able to access approximately $3.5 million of the $4 million with the rest being a cost to the district.

Bittante clarified that the overspending was not a reflection of the contractor as they came in on budget. Their budget just should have been smaller.

“They came in on target with money that they were given, but we weren’t able to access all the funds.”

She adds that increased oversight will occur on all future capital projects to ensure any overspending is identified and taken care of immediately.

At Tuesday’s meeting, the SD71 school board voted in favour of transferring $1,450,000 of unrestricted operating surplus to cover the overspend.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Fire torches large portable bathroom in Qualicum Beach

RCMP: ‘Senseless act has left taxpayers on the hook for the significant damages’

City of Parksville offers information about coronavirus

Says chances of getting COVID-19 locally are currently low

Popular TV series ‘Chesapeake Shores’ renewed for season five

Hallmark Channel show to return to filming in Parksville Qualicum Beach area

Shantz finishes second, happy for B.C. curling champ

Michayluk finally a victor at provincial women’s senior bonspiel

RDN bylaw allows people experiencing homelessness to camp overnight in some parks

Board of directors unanimously passes park use regulations bylaw

Fashion Fridays: Tammy’s big makeover

Kim XO, helps to keep you looking good on Fashion Fridays on the Black Press Media Network

Nanaimo woman leaves friend’s home, now considered missing

Ashley Sheppard, 31, has not been heard from since Feb. 10

Ryan nets hat trick in return as Senators beat Canucks 5-2

Ottawa winger received assistance for admitted alcohol problem

Speaker ‘will not tolerate illegal activity’ on B.C. legislature grounds, says chief of staff

Chief of staff to the B.C. speaker Alan Mullen says situation with demonstrators appears ‘fluid’

Wet’suwet’en hereditary chiefs meet with provincial, federal ministers

Neither party speaking on the groundwork laid for tomorrow’s talks

‘The project is proceeding’: Horgan resolute in support of northern B.C. pipeline

B.C. premier speaks as talks scheduled with Wet’suwet’en hereditary chiefs

Dates back to 2009: Calgary police lay charges in fraud involving semi-trucks

Three people from Calgary are facing charges that include fraud over $5,000

Comox 442 Squadron carries out two sea rescue missions north of Vancouver Island

Submitted by Lt. Alexandra Hejduk Special to Black Press 442 Transport and… Continue reading

Most Read