Diversion tunnels have been completed to redirect the Peace River during low water this summer and fall, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

B.C. Hydro’s Site C set back by COVID-19, foundation changes

Peace River diversion still on track for this fall

B.C. Hydro’s plan to have the third dam on the Peace River complete and in service by 2024 has been set back by work scaling down due to COVID-19 restrictions on construction projects, and additional foundation strengthening for the powerhouse and spillway.

In a progress report filed with the B.C. Utilities Commission July 31, B.C. Hydro CEO Chris O’Riley says the Site C project is still on track to divert the Peace River through a pair of tunnels and begin in-river work. But that too has been complicated by geological conditions. The financial impact of the coronavirus delays and additional work will be better known in the fall, O’Riley said.

“Pandemic-related delays will present further cost pressure on the budget,” O’Riley wrote in a letter to BCUC chair David Morton. “As the evolution of the pandemic is uncertain and the date of resolution is unknown, various cost and scheduled impact scenarios continue to be assessed and refined as part of the re-baselining process.”

The incoming NDP government reluctantly decided to carry on with Site C, after former premier Christy Clark vowed to push the project “past the point of no return” before the 2017 B.C. election. In doing so, Premier John Horgan approved an updated cost estimate of $10.7 billion to complete it, an increase of about $1 billion from the initial estimate.

RELATED: Site C dam project carries on under NDP government

RELATED: NDP pays off $1.1B in B.C. Hydro debt, seeks rate cut

RELATED: After losing at every level, West Moberly sues again

Now the combined effects of COVID-19 and a series of problems have pushed the cost up by an amount not yet known. Those issues included changes to the main civil works contract, increased costs of reservoir clearing, power line construction and highway realignment, and first nations treaty infringement claims and an injunction application.

“Towards the end of December 2019, investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas,” O’Riley wrote.

Before the COVID-19 pandemic, Site C was on track for completion by fall 2023 and full service to the B.C. Hydro grid by 2024.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureCoronavirusSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Sand sculptor creates special eagle head in Qualicum Beach

Kaube fashions work behind Civic Centre

Qualicum Beach seniors hiking group tackles alpine trails

Annual trip involves taking helicopter to remote locations

Parksville asks for help identifying veterans for special banner project

Program to honour veterans whose names are listed on Parksville cenotaph

QUIZ: Do you know the truth?

In what has been described as a post-truth era, how much do you know about truth and lies?

NHL playoffs: Canucks to meet St. Louis Blues in Round 1

Vancouver takes on defending champs beginning Wednesday

Process begins to try to get lookout trail over Nanoose Bay authorized

Regional District of Nanaimo staff will report back to parks and trails committee

Simon Cowell breaks his back falling from electric bike

Incident happened at his home in California

Poetry contest started for Vancouver Island poets

“We’re such a unique group,” says founder on why she wanted to start the collective

Unofficial holidays: the weird and wonderful things people celebrate around the world

On any given day of the year, there are several strange, silly or serious holidays to observe

Island MP says fish harvester benefit needs a wider application window

Courtenay-Alberni’s Gord Johns requests expanded application period for fish harvester benefits

Missing teen visiting Courtenay found safe

She had last been seen going for a walk on Aug. 6

Moving on: Tanev scores 11 seconds into OT as Canucks oust Wild

Vancouver beats Minnesota 5-4 to move into first round of NHL playoffs

Most Read