Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

Ravensong Waterdancers perform well at regional meet

Mable Moran Regional Championships held in Richmond

UPDATE: Police rule out alcohol, distraction in fatal crash in Nanoose

Passenger of fatal crash still in critical condition following crash in Nanoose Bay on Friday

Refugee family meets supporters at Parksville’s Ascension Church

MP calls congregation’s efforts an “inspiring story for all Canadians”

MLA Stilwell chairing B.C. Liberals’ new affordability committee

Opposition thinking about election readiness

Qualicum Beach approves waterfront mobile vendor licences

Waterfront will have multiple food vendors this summer

UPDATED: 9 killed, 16 injured after van hits pedestrians in Toronto

Toronto police say nine people have died and 16 are injured

Parksville resident interrupts break and enter

Two reported break and entries on Gaetjen Street

Judith Guichon steps down as Lieutenant Governor of B.C.

Election decision didn’t make her best moments from the past six years

Vancouver to rake in $30 million in empty homes tax in first year

The tax is the first of its kind in Canada, and was intended to address the city’s near-zero vacancy rate

LGBTQ advocates turn Victoria SOGI protest into dance party

Counter-protest outnumbers anti-SOGI activists on lawn of B.C. legislature

B.C.’s snowpack continues to increase, melting delayed

River Forecast Centre official says sudden melting further into the season could cause flooding

Another B.C. First Nation voices support for Kinder Morgan pipeline

Simpcw First Nation claims people living on one-third of pipeline route support the project

Scooter crash leaves Island man with critical injuries

RCMP said a truck was making a left-hand turn when it collided with the scooter travelling through the intersection

Most Read