Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC HydroBC legislatureSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Qualicum Beach council moves forward on comprehensive land-use plan for contentious parcel

March takes place in Qualicum Beach against development of ‘Greenbelt’ land

Parksville woman reaches quarter-finals of ‘Maxim’ magazine cover girl contest

Boldo advances through wildcard round; voting ends July 16

Ghost Light continues to shine at Village Theatre in Qualicum Beach

ECHO Players aim to recover revenue lost due to COVID-19 pandemic

Quacker of a conundrum: Case of the missing rubber duckies in Parksville

Couple hopes for return of their stolen yellow friends

COVID-19 pandemic estimated to lead to $2-million loss for RDN Transit

Regional District of Nanaimo has been seeing gradual rider increase since mid-May

21 new COVID-19 cases confirmed in B.C. as virus ‘silently circulates’ in broader community

Health officials urge British Columbians to enjoy summer safely as surge continues

Tough time for tree fruits as some B.C. farm products soar

Province reports record 2019 sales, largely due to cannabis

Nanaimo NightOwls will play ball under the lights next season

West Coast League baseball club unveils its team name

PHOTOS: Inside a newly-listed $22M mega-mansion on ALR land in B.C.

The large home, located on ALR land, is one of the last new mansions to legally be built on ALR land

‘Let’s all do a self-check’: Okanagan mayor reacts to racist vandalism targeting local family

Home of Indo-Canadian family in Summerland was targeted on evening of July 13

Province agrees to multimillion-dollar payout for alleged victims of Kelowna social worker

Robert Riley Saunders is accused of misappropriating funds of children — often Indigenous — in his care

Feds fund safe drug supply pilot program for Cowichan

The opioid overdose crisis continues to be one of the most serious public health crises

B.C. businessman David Sidoo gets 3 months behind bars for college admissions scam

Sidoo was sentenced for hiring someone take the SATs in place of his two sons

Thousands of dollars in stolen rice found in B.C. warehouse

Police raid seizes $75,000 in ‘commercial scale’ theft case

Most Read