Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

RDN adopts new bylaw to prevent backflow

Board wants to avoid legal liability

Former Parksville Generals player lands head coaching gig in Norway

New position is a dream come true for Henry Acres

Parksville resort fire caused by flammable gas used to extract oil from cannabis

Investigators detail reasons for explosion and blaze that destroyed building

Suspect arrested following gunpoint robbery in Qualicum Beach

Stop and Shop Grocery was robbed June 5; man now in custody

UPDATED: Wildfire burning near Taylor Flats in the Alberni Valley

Fire is located close to Highway 4 near Sproat Lake

PHOTOS: Elusive ‘ghost whale’ surfaces near Campbell River

Ecotourism operator captures images of the rare white orca

Suicide confirmed in case of B.C. father who’d been missing for months

2018 disappearance sparked massive search for Ben Kilmer

Victoria mom describes finding son ‘gone’ on first day of coroners inquest into overdose death

Resulting recommendations could change handling of youth records amidst the overdose crisis

B.C. church’s Pride flag defaced for second time in 12 days

Delta’s Ladner United Church says it will continue to fly the flag for Pride month

Otters devour 150 trout at Kootenay hatchery

The hatchery has lost close to 150 fish in the past several months

Dash-cam video in trial of accused cop killer shows man with a gun

Footage is shown at trial of Oscar Arfmann, charged with killing Const. John Davidson of Abbotsford

Eight U.S. senators write to John Horgan over B.C. mining pollution

The dispute stems from Teck Resources’ coal mines in B.C.’s Elk Valley

Threats charge against Surrey’s Jaspal Atwal stayed

Atwal, 64, was at centre of controversy in 2018 over his attendance at prime minister’s reception in India

Anti-vaxxer Robert F. Kennedy Jr. to speak in Surrey

He’s keynote speaker at Surrey Environment and Business Awards luncheon by Surrey Board of Trade Sept. 17

Most Read