Site C dam project design has been changed to eliminate a separate bridge across the Peace River

Permits approved for Site C hydro dam

BC Hydro negotiating compensation with aboriginal communities, B.C. cabinet to decide soon whether $8 billion project will go ahead

VICTORIA – Both the federal and provincial governments have issued environmental assessment certificates for BC Hydro’s Site C dam, the proposed third hydroelectric project on the Peace River in northeastern B.C.

The approvals include dozens of legally binding conditions, including a $20 million farmland enhancement fund to offset river bottom land that would be flooded, and compensation for local aboriginal groups whose historic treaty rights to hunting, fishing and trapping would be affected.

Cost of the project, last estimated by BC Hydro at $7.9 billion, will factor into a final decision by the B.C. cabinet whether to go ahead with the dam. Energy Minister Bill Bennett has indicated he expects the final investment decision to be made by the end of 2014, and if it’s approved, work would begin immediately.

Among the 77 B.C. conditions is an aboriginal business participation strategy to share the estimated 10,000 person-years of construction work the dam project would generate.

Seven aboriginal communities affected by the proposal have been offered cash and Crown land to compensate for land lost by construction of the dam. All are signatories to Treaty 8, which ensures their rights to hunt, trap and fish as they did before the treaty was signed in 1899. Officials say five of the seven are currently in negotiations.

Situated near Fort St. John and downstream of the W.A.C. Bennett and Peace Canyon dams, Site C’s 1,050-metre-long earthfill dam would create a reservoir 83 km long and two to three times the current width of the river.

It requires two power lines built in the same corridor as the existing line, and six water turbine generators that would produce enough electricity to power about 450,000 homes.

BC Hydro estimates that because Site C would use water held back in the existing Williston Lake reservoir, it would generate 35 per cent of the energy as the Bennett dam with only five per cent of the reservoir area.

 

Just Posted

Big Hearts to descend on the Tigh-Na-Mara Toy Drive

Annual event takes place Nov. 27 in Parksville

Man taken to hospital after driving off road in Qualicum Beach

51-year-old man from Port Alberni struck parked vehicle

City of Parksville rejected sharps disposal containers from Island Health

Mayor says cost of maintaining boxes too much for city

Parksville artist displays works inspired by a career in music

Owen O’Carroll’s ink works on display at Qualicum Art Supply & Gallery

Bye bye Bei Bei: Giant panda born in U.S. zoo heads to China

Panda heads back to China as part of cooperative breeding program

B.C. to advocate for frustrated, confused, unhappy cellphone users, says premier

Maple Ridge New Democrat Bob D’Eith to advocate for more affordable and transparent cellphone options

B.C. man who killed Belgian tourist near Boston Bar gets life in prison, no parole until 2042

Sean McKenzie pleaded guilty to second-degree murder of 28-year-old Amelie Christelle Sakkalis

Salvation Army kettle campaign targets $200,000 for Island residents in need

Goal is to raise $250,000 this year for Vancouver Island residents needing support

‘Very disrespectful’: B.C. first responder irked by motorists recording collisions on cellphones

Central Cariboo Search and Rescue deputy chief challenges motorists to break the habit

Daily cannabis linked to reduction in opioid use: B.C. researchers

Researchers looked at a group of 1,152 people in Vancouver who reported substance use and chronic pain

Port Alberni rallies for mill workers

Fundraisers helping ease the sting of five months without work

Island student lobbies school board for dress code consistency

Jaylene Kuo contacted school trustees after seeing dress guidelines at brother’s school

Most Read