Ian Anderson, CEO of Kinder Morgan, gestures during an interview at the company’s offices in Calgary in 2016. (THE CANADIAN PRESS/Jeff McIntosh)

Shovels could be in the ground on Trans Mountain by September, CEO says

Ian Anderson points to weeks likely required for NEB to reinstate 2016 regulatory record

The CEO of the Crown corporation building the Trans Mountain pipeline expansion says shovels could be in the ground by September following cabinet approval Tuesday of the long-delayed project.

Oil could be flowing in new segments of the pipeline between Edmonton and the West Coast by mid-2022, Ian Anderson said, about one year later than the timeline envisioned last August when the Federal Court of Appeal quashed its regulatory approval and halted all fieldwork.

“We’re excited, our shippers are excited and the communities we touch are excited along the pipeline corridor,” said the CEO of Trans Mountain Corp. during a conference call Wednesday.

“We’re confident now that our project will meet every standard, every regulation, every test and reflect the values and priorities and principles that we all care for as Canadians.”

The National Energy Board is being asked to reinstate the record from the previous regulatory proceeding in 2016 so that the project can be brought back to the same state of construction readiness as last summer, Anderson said, a process expected to take some weeks.

He said the fact the federal government owns the pipeline won’t change or hurry the process.

Two re-routing requests are still to be decided, he said, including one involving B.C.’s Coldwater reserve, although those processes aren’t expected to affect the timeline.

He said contractors are being mobilized, pipe is being stockpiled in yards in Alberta and B.C. and the Burnaby terminal on the West Coast is being made ready so that construction work can begin there as soon as permitted.

Anderson said there is no update on the last estimated project cost of $7.4 billion, while conceding that “time is money.”

Earlier Wednesday, Finance Minister Bill Morneau told a Calgary business audience the best way to convince a skeptical oilpatch that the expansion will actually be built is to go ahead and build it.

“What we said yesterday was that we renewed that (pipeline) approval,” Morneau told reporters.

“What’s happening today is we’re back at work. The re-permitting is happening starting today. We are going to get work going this construction season. I want people in Alberta and people across the country to know that intent is real.”

Last August, the Federal Court of Appeal ripped up the original federal approval of the 590,000-barrel-per-day expansion, citing incomplete Indigenous consultations and a faulty environmental review.

Dan Healing, The Canadian Press

Like us on Facebook and follow us on Twitter

Just Posted

Nanoose Bay carver goes all-in on projects

Bellis creates eight-foot totem as Christmas gift for wife

Oceanside RCMP auxiliary officer earns top honour for volunteer work

Dally presented special award by Island Commander

‘A really kind person’: Parksville’s Nick Major remembered by instructor

Outpouring of support in the days following death of young man

Qualicum Beach council talks East Village plans, traffic calming

Ideas floated for village as a pedestrian-friendly area attracting tech, digital arts industry

VIDEO: Young couple found dead in northern B.C. had been shot, police say

Chynna Noelle Deese of the U.S. and Lucas Robertson Fowler of Australia were found along Highway 97

VIDEO: Man found dead near B.C. teens’ truck could be linked to a double homicide

RCMP said they are looking for Kam McLeod, 19, and Bryer Schmegelsky, 18, of Port Alberni

Latest plan is to fly trapped fish by helicopter over Big Bar slide

Multi-pronged plan set in motion to freesalmon blocked by landslide in the Fraser River

Family of missing B.C. senior with dementia frustrated with situation, heartened by community support

Nine days since Grace was last seen the question remains: ‘How can an 86-year-old just disappear?’

Police ask for help locating missing men last seen in South Surrey

Jeep that Richard Scurr and Ryan Provencher were in has been located unoccupied in Logan Lake: RCMP

Islanders have new cancer screening option with $6.5 M diagnostic suite in Victoria

The Gordon Heys Family PET/CT Suite was unveiled at the BC Cancer Centre-Victoria

Unsealed record suggests U.S. man convicted of murdering Vancouver Island couple left DNA on zip tie in 1987

William Talbott is set to be sentenced Wednesday in the murders of Jay Cook and Tanya Van Cuylenborg

Vancouver Island teens missing after vehicle found ablaze near Dease Lake, BC

RCMP say a body discovered nearby not one of the missing teens

B.C. Ferries crew member’s medical emergency causes cancellations on Nanaimo route

One sailing from West Vancouver and one sailing from Nanaimo cancelled Monday

Most Read